About

After experiencing two historic floods in less than two years, Ellicott City was in desperate need of plan for flood mitigation that enhances public safety, retains the city's historic charm, and provides a sense of security to businesses, residents, and property owners. 

The Ellicott City Safe and Sound Plan encompasses those values as a guiding principle through its comprehensive and innovative approach to flood mitigation. The Plan outlines seven major infrastructure projects designed to reduce flooding in Historic Ellicott City. These projects include two water conveyance projects and five water detention projects throughout the watershed. When complete, these projects will work together to reduce the quantity and velocity of water on Main Street during major storm events.

Map of the Safe and Sound Flood Mitigation projects in Ellicott City.

Construction Projects

Title

H-7 Flood Mitigation Pond

Content

Completed in October 2022, the H-7 Pond was constructed on state land in a clover-leaf interchange at the intersection of Route 29 and Route 40/Baltimore National Pike in Ellicott City. While the pond will typically remain dry, it has the capacity to hold more than 4.2 million gallons of water, restricting the flow of water away from Historic Ellicott City. As part of this construction project, 110 trees and 1,800 native plants were planted.

Image
A timeline of the construction of the H7 flood mitigation pond project. Currently the project is considered complete.
Title

Quaker Mill Pond

Content

Completed in February 2023, the Quaker Mill pond was constructed along Rogers Avenue in Ellicott City. This detention pond has the capacity to hold more than 3.3 million gallons of water during storm events, restricting the flow of floodwaters away from Main Street. As part of this project, the County also planted 150 trees with this project, which enhances the stability of the embankment and efficacy of the pond. Click here to watch a video and learn more about the Quaker Mill Pond.

Image
A timeline of the construction of the Quaker Mill pond project. Currently the project is considered complete.
Title

H-4 Pond

Content

The H-4 Pond is a water detention pond that will be located along Frederick Road west of US29. Once complete, this project will have the capacity to hold more than 5.5 million gallons of water during storm events, directing water away from Historic Ellicott City.

Final design on this project is complete. Construction is scheduled to begin in Summer 2024.

Image
A timeline of the construction of the H4 pond project. Currently the project is scheduled to be completed in Summer of 2024..
Title

NC-3 Pond

Content

The NC-3 Pond is a water detention pond that will be located on the New Cut branch in Ellicott City. This project is anticipated to hold approximately 63-acre-feet of water, which is the equivalent of more than 20 million gallons of water.

The NC-3 Pond is currently in the final design and permitting stage. 

Image
A timeline of the construction of the NC-3 pond project. Currently the project is in the final permitting and design stage.
Title

T-1 Pond

Content

The T-1 Pond is a water detention pond that will be located on the Tiber tributary in Ellicott City. This project is anticipated to hold approximately 70-acre-feet of water, which is the equivalent of more than 22 million gallons of water.

The T-1 Pond is currently in the planning and preliminary design stage. 

Image
A timeline of the construction of the T-1 pond project. Currently the project is in the preliminary planning stage.
Title

Extended North Tunnel

Content

The Extended North Tunnel is a focal point of the EC Safe and Sound Plan. The North Tunnel is a water conveyance project that will carry flood waters from the West End of Ellicott City through an 18-foot-diameter, underground tunnel to the Patapsco River. This project will reduce the risk of flash flooding by intercepting water from the western portions of town and diverting it underground and away from Main Street.

Final design for the Extended North Tunnel is complete, and CSX Transportation has provided conceptual approval. Construction is scheduled to begin in Summer 2024.

Image
A timeline of the construction of the Extended North Tunnel project. Currently the project is scheduled to be completed in Summer of 2024.
Title

Maryland Avenue Culverts

Content

The Maryland Avenue Culverts are a water conveyance project that will install a new pair of pipe culverts from Lower Main Street into the Patapsco River. This project will better convey water from the Tiber River into the Patapsco River during severe weather events.

Final design for the Maryland Avenue Culverts is underway, and CSX Transportation has provided conceptual approval for this project.

Image
A timeline of the construction of the Maryland Avenue Culverts project. Currently the project is in the final permitting and design stage.

Flood Mitigation Strategy

Title

Collaborative Funding Efforts

Content

In conjunction with state and federal partners, the County has secured substantial funding to make these projects a reality. To date, the County has assembled more than $200 million in local, state, and federal funding to advance these flood mitigation projects. This includes being awarded a competitive, $75 million Water Infrastructure Finance and Innovation Act (WIFIA) loan through the Environmental Protection Agency. This significant commitment of local, state, and federal funding underscores the collaboration needed to advance this comprehensive plan.

Title

Expert Validation

Content

Our flood mitigation plan has received an endorsement from a national team of experts assembled by the U.S. Army Corps of Engineers (USACE). Their affirmation speaks to the soundness and feasibility of our chosen strategies.

Title

Developing the Plan

Content

Upon taking office in December 2018, County Executive Calvin Ball initiated the Ellicott City Safe and Sound Plan and immediately directed the Department of Public Works (DPW) to develop options for flood mitigation using those values as guiding principles. After analyzing over 70 potential scenarios, the County Executive selected the five options that best achieve the desired outcomes to present to the community for comment and discussion. The community was given an opportunity to comment on these options via email, the website, or at a public meeting on May 2, 2019.
 
After reviewing the comments and conferring with experts, County Executive Ball selected option 3G.7.0. This bold plan is the best available option to move forward with urgency, prioritize public safety, and build a model of resilience. This plan was reviewed by a national team of experts assembled by the Army Corps of Engineers. In their report, the Army Corps affirmed that the county is following a sound process and that the projects included in the county's plan can significantly reduce flood risk to Historic Ellicott City. 

Frequently Asked Questions

Flood Mitigation Plan

How will the county pay for these projects?

We have been and continue to actively pursue state and federal grants, and are also using county funds to pay for the projects. Since taking office, County Executive Ball has worked with partners at the state and federal level to secure more than $200 million in funding for flood mitigation and related projects in Ellicott City. This includes a $75 million WIFIA loan through the Environmental Protection Agency and more than $40 million in state funds.

 

When will construction be completed?

As of October 2023, two Safe and Sound projects have had construction completed: the H-7 and Quaker Mill Retention Ponds. Other projects will be completed as quickly as possible pending the completion of required design and permitting activities.

 

What impact will these projects have on businesses and residents in Ellicott City and on the West End?

The largest impact will be around the construction of the Maryland Avenue Culvert, which could lead to road closures on Maryland Avenue. The exact impact is still being evaluated. Other projects should cause minimal or no impacts to businesses or residents in Ellicott City. For businesses and residents on the West End, temporary lane closures for the construction of the new culverts are anticipated.

 

When will acquisitions be completed?

All of the buildings on lower Main Street that the county intended to acquire have been purchased.

 

The county included the 100-year storm and the July 2016 in the analysis. Why didn't you show how the improvements would perform in the May 2018 storm?

Based on modelling data, the July 2016 storm produced the worst flooding so this storm was used to benchmark the flood mitigation options.

Capital Projects

What does it mean when a bid is advertised?

When a bid is advertised, a date is selected for interested and qualified contractors to submit a proposal for the work. This task is managed by the Office of Procurement and Contract Administration, which collects applicable technical documents, and posts the opportunity in the public domain.

 

What's the difference between preliminary design and final design?

Preliminary design generally includes activities to develop and evaluate concepts for the proposed work, and select a concept. This typically includes development of a conceptual cost estimate, as well as design and construction schedules which inform future budget requests. Final Design builds upon the preliminary design, and includes all technical documentation required to construct the project. This includes all required permitting.

 

Why do capital projects take so long?

Planning work for a significant Capital Project may start several years before an improvement is realized and involves several steps. There is typically also significant coordination required with external entities that can add to the overall timeline.

 

Why are you not showing expected completion dates for the projects?

Estimated completion dates are most accurate once the permitting and bid processes are complete. As more accurate information is available, the tracker will be updated.

County-Owned Building Restoration

Are there plans to rebuild Caplan’s?

Since the County has acquired Caplan’s, significant measures have been implemented to stabilize the front portion of the building. This includes removing flood debris, installing permanent shoring and bracing, and planning for future improvements. The County plans to construct dry floodproofing at the new rear (south) side of the building and is proceeding with reconstruction of a resilient façade.

 

Why did Caplan’s get so damaged?

Caplan’s is situated at the bottom of the hill where Main Street turns, which makes Caplan’s both a focal point of the streetscape and more vulnerable to damage from flooding. Caplan’s is the first building along Lower Main Street that is built over the stream channel; and it has taken the brunt of the damage along the rear of the building from strong flood waters and storm debris.

 

What are the plans for the county-owned buildings on Lower Main Street?

The buildings purchased by the county will remain a public asset until all flood mitigation projects are complete. All of the structures over the stream channel will need to be demolished in order to remove constrictions. The county has completed a federal section 106 review in order to perform that work and is currently working on plans for renovation of those buildings. In the meantime, all of the building interiors have been cleared of storm debris and water-damaged finishes. Many storefronts along Main Street have been rebuilt with display windows in order to provide a weather resistant and attractive façade while final plans are developed and approved.

 

Can the existing buildings along Lower Main Street be restored to the pre-2018 flood conditions?

The buildings along Lower Main Street will need to change based on hydraulic studies. No first-floor structures can remain over the stream channels.

 

What work has been completed on Lower Main Street?

Extensive work has been ongoing on the county-owned buildings on Main Street:

  • All of the properties acquired by the county were initially assessed for structural integrity. Most buildings have also undergone some degree of clean out and/or repair activities.
  • New doors or windows were installed at 8081 Main Street (Tea on the Tiber), 8085 Main Street (Portalli’s), 8095 Main Street (Shoemaker Country) and 8111-8113 Main Street. Façade repairs and shadowboxes were also completed at 8085 Main Street, 8095 Main Street, and 8111-8113 Main Street.
  • Several buildings, including the former Caplan’s Department Store at 8125 Main Street had basements filled in to further ensure structural integrity. Mold remediation work was also completed as needed.

Stay Connected!

Sign up for the County Executive's weekly newsletter and stay up to date on everything Howard County.
 

Zip Code