About
After experiencing two historic floods in less than two years, Ellicott City was in desperate need of plan for flood mitigation that enhances public safety, retains the city's historic charm, and provides a sense of security to businesses, residents, and property owners.
The Ellicott City Safe and Sound Plan encompasses those values as a guiding principle through its comprehensive and innovative approach to flood mitigation. The Plan outlines seven major infrastructure projects designed to reduce flooding in Historic Ellicott City. These projects include two water conveyance projects and five water detention projects throughout the watershed. When complete, these projects will work together to reduce the quantity and velocity of water on Main Street during major storm events.

Construction Projects
H-7 Flood Mitigation Pond
Completed in October 2022, the H-7 Pond was constructed on state land in a clover-leaf interchange at the intersection of Route 29 and Route 40/Baltimore National Pike in Ellicott City. While the pond will typically remain dry, it has the capacity to hold more than 4.2 million gallons of water, restricting the flow of water away from Historic Ellicott City. As part of this construction project, 110 trees and 1,800 native plants were planted.

Quaker Mill Pond
Completed in February 2023, the Quaker Mill pond was constructed along Rogers Avenue in Ellicott City. This detention pond has the capacity to hold more than 3.3 million gallons of water during storm events, restricting the flow of floodwaters away from Main Street. As part of this project, the County also planted 150 trees with this project, which enhances the stability of the embankment and efficacy of the pond. Click here to watch a video and learn more about the Quaker Mill Pond.

H-4 Pond
The H-4 Pond is a water detention pond that will be located along Frederick Road west of US29. Once complete, this project will have the capacity to hold more than 5.5 million gallons of water during storm events, directing water away from Historic Ellicott City.
Final design on this project is complete. Construction is scheduled to begin in Summer 2024.

NC-3 Pond
The NC-3 Pond is a water detention pond that will be located on the New Cut branch in Ellicott City. This project is anticipated to hold approximately 63-acre-feet of water, which is the equivalent of more than 20 million gallons of water.
The NC-3 Pond is currently in the final design and permitting stage.

T-1 Pond
The T-1 Pond is a water detention pond that will be located on the Tiber tributary in Ellicott City. This project is anticipated to hold approximately 70-acre-feet of water, which is the equivalent of more than 22 million gallons of water.
The T-1 Pond is currently in the planning and preliminary design stage.

Extended North Tunnel
The Extended North Tunnel is a focal point of the EC Safe and Sound Plan. The North Tunnel is a water conveyance project that will carry flood waters from the West End of Ellicott City through an 18-foot-diameter, underground tunnel to the Patapsco River. This project will reduce the risk of flash flooding by intercepting water from the western portions of town and diverting it underground and away from Main Street.
Final design for the Extended North Tunnel is complete, and CSX Transportation has provided conceptual approval. Construction is scheduled to begin in Summer 2024.

Maryland Avenue Culverts
The Maryland Avenue Culverts are a water conveyance project that will install a new pair of pipe culverts from Lower Main Street into the Patapsco River. This project will better convey water from the Tiber River into the Patapsco River during severe weather events.
Final design for the Maryland Avenue Culverts is underway, and CSX Transportation has provided conceptual approval for this project.

Flood Mitigation Strategy
Collaborative Funding Efforts
In conjunction with state and federal partners, the County has secured substantial funding to make these projects a reality. To date, the County has assembled more than $200 million in local, state, and federal funding to advance these flood mitigation projects. This includes being awarded a competitive, $75 million Water Infrastructure Finance and Innovation Act (WIFIA) loan through the Environmental Protection Agency. This significant commitment of local, state, and federal funding underscores the collaboration needed to advance this comprehensive plan.
Expert Validation
Our flood mitigation plan has received an endorsement from a national team of experts assembled by the U.S. Army Corps of Engineers (USACE). Their affirmation speaks to the soundness and feasibility of our chosen strategies.
Developing the Plan
Upon taking office in December 2018, County Executive Calvin Ball initiated the Ellicott City Safe and Sound Plan and immediately directed the Department of Public Works (DPW) to develop options for flood mitigation using those values as guiding principles. After analyzing over 70 potential scenarios, the County Executive selected the five options that best achieve the desired outcomes to present to the community for comment and discussion. The community was given an opportunity to comment on these options via email, the website, or at a public meeting on May 2, 2019.
After reviewing the comments and conferring with experts, County Executive Ball selected option 3G.7.0. This bold plan is the best available option to move forward with urgency, prioritize public safety, and build a model of resilience. This plan was reviewed by a national team of experts assembled by the Army Corps of Engineers. In their report, the Army Corps affirmed that the county is following a sound process and that the projects included in the county's plan can significantly reduce flood risk to Historic Ellicott City.
Frequently Asked Questions
How will the county pay for these projects?
We have been and continue to actively pursue state and federal grants, and are also using county funds to pay for the projects. Since taking office, County Executive Ball has worked with partners at the state and federal level to secure more than $200 million in funding for flood mitigation and related projects in Ellicott City. This includes a $75 million WIFIA loan through the Environmental Protection Agency and more than $40 million in state funds.
When will construction be completed?
As of October 2023, two Safe and Sound projects have had construction completed: the H-7 and Quaker Mill Retention Ponds. Other projects will be completed as quickly as possible pending the completion of required design and permitting activities.
What impact will these projects have on businesses and residents in Ellicott City and on the West End?
The largest impact will be around the construction of the Maryland Avenue Culvert, which could lead to road closures on Maryland Avenue. The exact impact is still being evaluated. Other projects should cause minimal or no impacts to businesses or residents in Ellicott City. For businesses and residents on the West End, temporary lane closures for the construction of the new culverts are anticipated.
When will acquisitions be completed?
All of the buildings on lower Main Street that the county intended to acquire have been purchased.
The county included the 100-year storm and the July 2016 in the analysis. Why didn't you show how the improvements would perform in the May 2018 storm?
Based on modelling data, the July 2016 storm produced the worst flooding so this storm was used to benchmark the flood mitigation options.