Howard County Executive Calvin Ball broke ground on the new Howard County Circuit Courthouse on June 24, 2019. The 238,000 square foot facility will be completed through a public-private partnership, the first for Howard County, and resolve deficiencies in the existing Courthouse, which was built 175 years ago and has numerous safety challenges that impact access to justice.  The new Courthouse is scheduled to be completed in July 2021.  While work is underway, questions and concerns about the construction process may be directed to:

Michael Cornell
Senior Superintendent / Site Supervisor
Clark Construction Group, LLC
7500 Old Georgetown Road
Bethesda, Maryland  20814-6133
Phone 301-272-8100

Rendering of new howard county courthouse from exterior pedestrian view

Courthouse Project Updates

Title

6/11/2021

Content

Work Performed:

 

  1. Completed installation of Millwork – Level 1, 3 & 4
  2. Completed installation of furniture – Level 1, 2, 3 & 4
  3. Continued final clean and punchout – Level 1, 2, 3 & 4
  4. Continued Commissioning Mechanical & Electrical
  5. Continued Commissioning Security and AV System
  6. Continued installation of Landscaping and Pavers
  7. Continued Build-out of the Kitchen

 

Work Next Week:

 

  1. Complete final clean and punchout – Level 1, 2, 3 & 4
  2. Complete Commissioning Mechanical & Electrical
  3. Complete Commissioning of Security and AV Systems
  4. Complete installation of Landscaping and Pavers
  5. Continue Build-out of the Kitchen
Title

6/4/2021

Content

Work Performed:

 

  1. Continued installation of Millwork – Level 1, 3 & 4
  2. Continued installation of furniture – Level 1, 2, 3 & 4
  3. Continued final clean and punchout – Level 1, 2, 3 & 4
  4. Continued Commissioning Mechanical & Electrical
  5. Continued Commissioning Security and AV System
  6. Continued installation of Landscaping and Pavers
  7. Continued Build-out of the Kitchen

 

Work Next Week:

 

  1. Complete installation of Millwork – Level 1,3 & 4
  2. Complete installation of furniture – Level 1, 2, 3 & 4
  3. Continue final clean and punchout – Level 1, 2, 3 & 4
  4. Continue Commissioning Mechanical & Electrical
  5. Continue Commissioning of Security and AV Systems
  6. Complete installation of Landscaping and Pavers
  7. Continue Build-out of the Kitchen
Title

5/28/2021

Content

Work Performed:

 

  1. Continued installation of Millwork – Level 1, 3 & 4
  2. Completed installation of metal panels – Atrium
  3. Continued installation of furniture – Level 1, 2, 3 & 4
  4. Continued final clean and punchout – Level 1, 2, 3 & 4
  5. Continued Commissioning Mechanical & Electrical
  6. Continued Commissioning Security and AV System
  7. Continued installation of Landscaping and Pavers
  8. Continued Build-out of the Kitchen

 

Work Next Week:

 

  1. Continue installation of Millwork – Level 1,3 & 4
  2. Continue installation of furniture – Level 1, 2, 3 & 4
  3. Continue final clean and punchout – Level 1, 2, 3 & 4
  4. Continue Commissioning Mechanical & Electrical
  5. Continue Commissioning of Security and AV Systems
  6. Continue installation of Landscaping and Pavers
  7. Continue Build-out of the Kitchen
Title

5/21/2021

Content

Work Performed:

 

  1. Continued installation of Millwork – Level 1, 3 & 4
  2. Continued installation of metal panels – Atrium
  3. Continued installation of furniture – Level 1, 2, 3 & 4
  4. Continued final clean and punchout – Level 1, 2, 3 & 4
  5. Continued Commissioning Mechanical & Electrical
  6. Continued Commissioning Security and AV System
  7. Continued installation of Landscaping and Pavers
  8. Continued Build-out of the Kitchen

 

Work Next Week:

 

  1. Continue installation of Millwork – Level 1,3 & 4
  2. Complete installation of metal panels – Atrium
  3. Continue installation of furniture – Level 1, 2, 3 & 4
  4. Continue final clean and punchout – Level 1, 2, 3 & 4
  5. Continue Commissioning Mechanical & Electrical
  6. Continue Commissioning of Security and AV Systems
  7. Continue installation of Landscaping and Pavers
  8. Continue Build-out of the Kitchen
Title

4/30/2021

Content

Work Performed:

 

  1. Continued installation of Millwork – Level 1, 3 & 4
  2. Continued installation of metal panels – Atrium
  3. Continued installation of furniture – Level 1, 2, 3 & 4
  4. Continued final clean and punchout – Level 2, 3 & 4
  5. Continued Commissioning Mechanical & Electrical
  6. Continued installation of Landscaping and Pavers

 

Work Next Week:

 

  1. Continue installation of Millwork – Level 1,3 & 4
  2. Continue installation of metal panels – Atrium
  3. Continue installation of furniture – Level 1, 2, 3 & 4
  4. Continue final clean and punchout – Level 2, 3 & 4
  5. Continue Commissioning Mechanical & Electrical
  6. Start Commissioning of Security and AV Systems
  7. Continue installation of Landscaping and Pavers
Title

4/16/2021

Content

Work Performed:

 

  1. Completed installation of terrazzo flooring – Level 1
  2. Continued installation of ceramic tile – Level 1
  3. Continued installation of Workstations – Level 1
  4. Continued installation of Millwork – Level 1, 3 & 4
  5. Continued installation of metal panels – Main Entrance
  6. Continued installation of furniture – Level 1, 2, 3 & 4
  7. Continued final clean and punchout – Level 2, 3 & 4
  8. Continued Commissioning Mechanical & Electrical
  9. Continued installation of Landscaping and Pavers

 

Work Next Week:

 

  1. Complete installation of ceramic tile – Level 1
  2. Complete installation of Workstations – Level 1
  3. Continue installation of Millwork – Level 1,3 & 4
  4. Continue installation of metal panels – Main Entrance
  5. Continue installation of furniture – Level 1, 2, 3 & 4
  6. Continue final clean and punchout – Level 2, 3 & 4
  7. Continue Commissioning Mechanical & Electrical
  8. Continue installation of Landscaping and Pavers
Title

4/2/2021

Content

Circuit Court for Howard County - progress update for 4/2/2021:

Work Performed:

  1. Continued point-up & finish paint – Level 1
  2. Continued installation of terrazzo flooring – Level 1
  3. Continued installation of ceiling tile – Level 1
  4. Continued installation of ceramic tile – Level 1
  5. Continued installation of casework – Level 1
  6. Completed installation of carpet – Level 1
  7. Continued installation of Workstations – Level 1
  8. Completed installation of Wood Doors – Level 1
  9. Continued installation of Millwork – Level 3 & 4
  10. Continued installation of metal panels – Main Entrance
  11. Continued installation of furniture – Level 1, 2, 3 & 4
  12. Continued final clean and punchout – Level 2, 3 & 4
  13. Continued installation of Landscaping and Pavers

 

Work Next Week:

  1. Complete point-up & finish paint – Level 1
  2. Complete installation of terrazzo flooring – Level 1
  3. Complete installation of ceiling tile – Level 1
  4. Continue installation of ceramic tile – Level 1
  5. Complete installation of casework – Level 1
  6. Complete installation of Workstations – Level 1
  7. Continue installation of Millwork – Level 3 & 4
  8. Continue installation of metal panels – Main Entrance
  9. Continue installation of furniture – Level 1, 2, 3 & 4
  10. Continue final clean and punchout – Level 2, 3 & 4
  11. Continue installation of Landscaping and Pavers

 

Image
Map of new Courthouse